2020 Off to a Flying Start at Glasgow Golf Club.

3rd Feb 2020

January 2020 proved to be a productive period for the Glasgow Golf Club construction site.

The East Wing first floor has been formed, installation of the main building steel work has commenced and the North elevation scaffold has been altered to allow the foundations for the extension to be constructed. This work will pave the way for significant activity during February.

Steelwork will continue which allows the old first floor in the main building to be replaced with a new concrete slab. This new floor will provide the necessary platform to construct the roof. We will also see work commencing on the new extension foundations.

Site activity will start to significantly increase over the next few months as we start to reinstate the Killermont House Clubhouse.

Doig+Smith is delighted to play a significant role in this restoration project, having been appointed by Glasgow Golf Club to provide its services in Project Management, Quantity Surveying and Principal Designer.

 